2026-08-10specificno outcome documentHPC MW
Phased delivery schedule, with the initial 96 IT MW expected in December 2027 and full 191 IT MW deployment expected by June 2028, leveraging Riot's existing, fully approved interconnection at the Rockdale campus.
- Projected
- 96 MW December 2027; 191 MW June 2028, by 2028-06-30
- Actual
- no outcome document yet
- Variance
- not resolved
Said in 8-K EX-99.1 2026-08-10 (Q2 2026 results), grade verified. No outcome document has been read for this statement yet.
2026-08-10specificno outcome documentHPC MW
Construction is now underway on the 25 MW expansion, with the 10 MW Phase 3 on track for delivery in November 2026 and the 15 MW Phase 4 to follow in May 2027, at which point AMD's total contracted capacity of 50 MW will be fully deployed.
- Projected
- 10 MW November 2026; 15 MW May 2027, by 2027-05-31
- Actual
- no outcome document yet
- Variance
- not resolved
Said in 8-K EX-99.1 2026-08-10 (Q2 2026 results), grade verified. No outcome document has been read for this statement yet.
2026-03-02specificsettledMW
We are targeting the Kentucky Facility to reach a total capacity of approximately 232 MW through the remainder of 2026, with additional expansion anticipated.
- Projected
- 232 MW developed capacity in Kentucky, by 2026-12-31
- Actual
- 192 MW developed at 2026-06-30 (137 MW at the 10-K date); unresolved as of 2026-06-30
- Variance
- not computed
The outcome document says: As of June 30, 2026, we had a total deployed hash rate capacity of 44.4 EH/s, as compared to 38.5 EH/s as of December 31, 2025, an increase of 15.3%. During the six months ended June 30, 2026, we mined 3,060 bitcoin, reflecting an increase of 104 bitcoin compared to the 2,956 bitcoin mined during the six months ended June 30, 2025.
Said in 10-K FY2025 (filed 2026-03-02), grade verified. Outcome from 10-Q Q2 2026 (filed 2026-08-10), grade verified.
2026-01-16specificsettledHPC MW
an initial deployment of 25 MW of critical IT load capacity to be delivered in phases beginning in January 2026 and completing in May 2026
- Projected
- 25 MW to AMD, by 2026-05
- Actual
- 5 MW delivered January 2026 and 20 MW delivered May 2026; 'on time and on budget' as of 2026-05-31
- Variance
- not computed
The outcome document says: Construction is now underway on the 25 MW expansion, with the 10 MW Phase 3 on track for delivery in November 2026 and the 15 MW Phase 4 to follow in May 2027, at which point AMD's total contracted capacity of 50 MW will be fully deployed.
Said in 8-K EX-99.1 2026-01-16, grade verified. Outcome from 8-K EX-99.1 2026-08-10 (Q2 2026 results), grade verified.
2025-05-01specificsettledMW
Construction work on the substation, to be completed in early 2026, also continues and will bring a total of 1.0 GW of power capacity online once completed.
- Projected
- 1.0 GW at Corsicana, by 2026-03-31
- Actual
- 10-Q Q2 2026 still describes Corsicana as 'currently equipped to provide up to approximately 400 MW ... upon completion, is expected to have a total of approximately one gigawatt'; substation completion not confirmed in reviewed filings as of 2026-06-30
- Variance
- not computed
The outcome document says: The Corsicana Facility is currently equipped to provide up to approximately 400 MW of developed capacity for Bitcoin Mining, and upon completion, is expected to have a total of approximately one gigawatt (“GW”) of developed capacity available for high-density compute workloads.
Said in 8-K EX-99.1 2025-04-28 (Q1 2025 results, dated May 1, 2025), grade verified. Outcome from 10-Q Q2 2026 (filed 2026-08-10), grade verified.
2025-01-21directionalsettledHPC MW
Riot is launching a formal process to evaluate the feasibility of developing the approximately 600 megawatts ("MW") of remaining power capacity at the Company's Corsicana Facility for artificial intelligence ("AI")/high-performance computing ("HPC") uses.
- Projected
- 600 MW at Corsicana for AI/HPC
- Actual
- first leases (241 MW) signed at Rockdale, not Corsicana; Corsicana full campus under non-binding LOI as of 2026-08-10 as of 2026-08-10
- Variance
- not computed
The outcome document says: AMD (50 IT MW) Leading Frontier AI Lab (191 IT MW) Total (241 IT MW) Rockdale Pro Forma Critical IT MW Leased
Said in 8-K EX-99.1 2025-01-21, grade verified. Outcome from 8-K EX-99.2 2026-08-10 (Q2 2026 earnings deck), grade verified.