Aug 10, 2026specificno outcome documentfilings and press releasesHPC MW
Phased delivery schedule, with the initial 96 IT MW expected in December 2027 and full 191 IT MW deployment expected by June 2028, leveraging Riot's existing, fully approved interconnection at the Rockdale campus.
- Projected
- 96 MW December 2027; 191 MW June 2028, by Jun 30, 2028
- Actual
- no outcome document yet
- Variance
- not resolved
Said in 8-K EX-99.1 Aug 10, 2026 (Q2 2026 results), grade verified. No outcome document has been read for this statement yet.
Aug 10, 2026specificno outcome documentfilings and press releasesHPC MW
Construction is now underway on the 25 MW expansion, with the 10 MW Phase 3 on track for delivery in November 2026 and the 15 MW Phase 4 to follow in May 2027, at which point AMD's total contracted capacity of 50 MW will be fully deployed.
- Projected
- 10 MW November 2026; 15 MW May 2027, by May 31, 2027
- Actual
- no outcome document yet
- Variance
- not resolved
Said in 8-K EX-99.1 Aug 10, 2026 (Q2 2026 results), grade verified. No outcome document has been read for this statement yet.
Mar 2, 2026specificstill openfilings and press releasesMW
We are targeting the Kentucky Facility to reach a total capacity of approximately 232 MW through the remainder of 2026, with additional expansion anticipated.
- Projected
- 232 MW developed capacity in Kentucky, by Dec 31, 2026
- Actual
- 192 MW developed at Jun 30, 2026 (137 MW at the 10-K date); unresolved as of Jun 30, 2026
- Variance
- not resolved
The outcome document says: The Kentucky Facility currently provides approximately 192 MW of developed capacity.
Said in 10-K FY2025 (filed Mar 2, 2026), grade verified. Outcome from 10-Q Q2 2026 (filed Aug 10, 2026), grade verified.
Jan 16, 2026specificsettledfilings and press releasesHPC MW
an initial deployment of 25 MW of critical IT load capacity to be delivered in phases beginning in January 2026 and completing in May 2026
- Projected
- 25 MW to AMD, by 2026-05
- Actual
- 5 MW delivered January 2026 and 20 MW delivered May 2026; 'on time and on budget' as of May 31, 2026
- Variance
- not computed
The outcome document says: Completed delivery of the initial 25 critical IT MW to AMD on time and on budget
Said in 8-K EX-99.1 Jan 16, 2026, grade verified. Outcome from 8-K EX-99.1 Aug 10, 2026 (Q2 2026 results), grade verified.
May 1, 2025specificsettledfilings and press releasesMW
Construction work on the substation, to be completed in early 2026, also continues and will bring a total of 1.0 GW of power capacity online once completed.
- Projected
- 1.0 GW at Corsicana, by Mar 31, 2026
- Actual
- 10-Q Q2 2026 still describes Corsicana as 'currently equipped to provide up to approximately 400 MW ... upon completion, is expected to have a total of approximately one gigawatt'; substation completion not confirmed in reviewed filings as of Jun 30, 2026
- Variance
- not computed
The outcome document says: The Corsicana Facility is currently equipped to provide up to approximately 400 MW of developed capacity for Bitcoin Mining, and upon completion, is expected to have a total of approximately one gigawatt (“GW”) of developed capacity available for high-density compute workloads.
Said in 8-K EX-99.1 Apr 28, 2025 (Q1 2025 results, dated May 1, 2025), grade verified. Outcome from 10-Q Q2 2026 (filed Aug 10, 2026), grade verified.
Jan 21, 2025directionalsettledfilings and press releasesHPC MW
Riot is launching a formal process to evaluate the feasibility of developing the approximately 600 megawatts ("MW") of remaining power capacity at the Company's Corsicana Facility for artificial intelligence ("AI")/high-performance computing ("HPC") uses.
- Projected
- 600 MW at Corsicana for AI/HPC
- Actual
- first leases (241 MW) signed at Rockdale, not Corsicana; Corsicana full campus under non-binding LOI as of Aug 10, 2026 as of Aug 10, 2026
- Variance
- not computed
The outcome document says: AMD (50 IT MW) Leading Frontier AI Lab (191 IT MW) Total (241 IT MW) Rockdale Pro Forma Critical IT MW Leased
Said in 8-K EX-99.1 Jan 21, 2025, grade verified. Outcome from 8-K EX-99.2 Aug 10, 2026 (Q2 2026 earnings deck), grade verified.