Jul 14, 2026specificstill openfilings and press releasesHPC MW
175 MW of critical IT load with deliveries expected to begin in Q4 2027 to a high-investment-grade tenant
- Projected
- 175 MW critical IT delivered starting Q4 2027, by Dec 31, 2027
- Actual
- unresolved; as of Aug 6, 2026 the company reported it had 'Ordered and pre-paid all long-lead items to meet Sandersville RFS date' and that the anticipated equity portion was fully funded as of Aug 6, 2026
- Variance
- not resolved
The outcome document says: Ordered and pre-paid all long-lead items to meet Sandersville RFS date ... Anticipated equity portion of Sandersville project has been fully funded
The outcome document reports preparation, not delivery: 'Ordered and pre-paid all long-lead items to meet Sandersville RFS date', and the anticipated equity portion of the project fully funded. Deliveries at Sandersville are expected to begin in Q4 2027, so the statement cannot resolve before then.
Said in 8-K EX-99.1 Jul 14, 2026 (Sandersville lease press release), grade verified. Outcome from 8-K EX-99.1 Aug 6, 2026 (Q3 FY2026 results), grade verified.
Jul 14, 2026specificstill openfilings and press releasesrevenue
Expected cumulative NOI contribution margin of nearly 100%, or an average annual NOI contribution of approximately $330 million
- Projected
- about $330 million average annual NOI from the Sandersville lease, over the 20-year initial term from Q4 2027
- Actual
- unresolved (lease not yet commenced) as of Sep 6, 2026
- Variance
- not resolved
The lease has not commenced, so none of the contracted revenue has been earned. The outcome document reports the project's funding and construction status and no revenue under this lease.
Said in 8-K EX-99.1 Jul 14, 2026 (Sandersville lease press release), grade verified. Outcome from 8-K EX-99.1 Jul 14, 2026 (Sandersville lease press release). No outcome sentence is stored, so the outcome was not string-checked.
Feb 5, 2026directionalsettledfilings and press releasesMW
We strengthened our financial foundation, secured up to 890 megawatts of high-quality utility potential capacity in the Houston region, and materially advanced our Sandersville site with the acquisition of an additional 122-acre parcel as we progress toward AI tenancy.
- Projected
- up to 890 MW of utility capacity in the Houston region (Texas), no date stated
- Actual
- 585 MW of ERCOT-approved capacity by May 2026 (including ERCOT approval of 300 MW at Brazoria); July 2026: Texas portfolio described as 'up to 885 MW of secured and planned power capacity' as of Jul 14, 2026
- Variance
- not computed
The outcome document says: Doubled MW under contract year-over-year including 585 MW of ERCOT-approved capacity
Said in 8-K EX-99.1 Feb 5, 2026 (Q1 FY2026 results), CEO quote, grade verified. Outcome from 8-K EX-99.1 May 11, 2026 headline and CEO quote; 8-K EX-99.1 Jul 14, 2026, grade verified.
Nov 25, 2025directionalsettledfilings and press releaseshashrate
We expect to continue increasing our computing power through calendar year 2025 and beyond as we expand infrastructure at our owned sites in Tennessee and across our portfolio of data centers in Georgia, Mississippi, and Wyoming, while also pursuing regional expansion opportunities and evaluating strategic acquisition targets.
- Projected
- continue increasing computing power through calendar year 2025 and beyond; no figure is stated, by 2026 and beyond
- Actual
- Average hashrate declined: 42.6 EH/s in June 2026 (10-Q) and 38.6 EH/s average operating in July 2026 (monthly update) versus 45.6 EH/s, the September 2025 final-month average as of Jul 31, 2026
- Variance
- not computed
The outcome document says: During June 2026, our operating mining units produced an average computing power of 42.6 exahash per second (“EH/s”), following our achievement of a peak hashrate of 50 EH/s during fiscal year 2025.
Said in 10-K FY2025 (fiscal year ended Sep 30, 2025), filed Nov 25, 2025, grade verified. Outcome from 10-Q Q3 FY2026 (quarter ended Jun 30, 2026), filed Aug 6, 2026, grade verified.
Dec 3, 2024specificsettledfilings and press releaseshashrate
We are currently developing an additional 211.5 MW across the portfolio, which is expected to support approximately 50 EH/s of mining capacity.
- Projected
- 50 EH/s, no date stated (context: 'through the end of 2024 and beyond')
- Actual
- 50 EH/s operational hashrate reached June 2025 as of Jun 30, 2025
- Variance
- 0.0%, on the projectionfrom 50 EH/s projected against 50 EH/s reported
The outcome document says: We reached 50 EH/s of operational hashrate in June, becoming the first public company to do so exclusively with American infrastructure, while achieving record basic EPS of $0.90 and nearly $200 million in revenue.
Said in 10-K FY2024, filed Dec 3, 2024, Item 1 Business, grade verified. Outcome from 8-K EX-99.1 Aug 8, 2025 (Q3 FY2025 results), grade verified.