GTA Gigafactory (BUZZ HPC, planned)

HIVE ON

Approximate area: the filing names only the state or country, not the site.

Imagery: NASA Blue Marble, a 2004 global composite. No single imagery date applies, and the site may have changed since. A flat view of the ground: no terrain.

Energized
not stated in the filings read
Nameplate
320 MW
Stage
announced
Power source
grid
Ownership
owned (planned)
Grid operator
IESO (Ontario; not stated)
Announced
May 18, 2026source dated May 18, 2026
Expected online
H2 2027source dated Jun 2, 2026a target, not proof of operation
Place named in the filing
ONlocated at the centre of its state

Source: HIVE 10-Q for the quarter ended Jun 30, 2026 (Q1 FY2027), filed Aug 14, 2026; read Sep 6, 2026.