operatinglocated at the centre of its city
Yguazu hydroelectric data center
HIVE Yguazu, Alto Parana
Approximate area: this is the town named in the filing, not the site.
Imagery: NASA Blue Marble, a 2004 global composite. No single imagery date applies, and the site may have changed since. A flat view of the ground: no terrain.
- Energized
- 195.2 MW
- Nameplate
- 200 MW
- Stage
- operating
- Power source
- hydro
- Ownership
- owned
- Grid operator
- ANDE (Administracion Nacional de Electricidad)
- Announced
- Jan 28, 2025source dated Jan 28, 2025
- Energized
- Apr 2025source dated Aug 14, 2026
- Place named in the filing
- Yguazu, Alto Paranalocated at the centre of its city
Source: HIVE 10-Q for the quarter ended Jun 30, 2026 (Q1 FY2027), filed Aug 14, 2026; read Sep 6, 2026.