announcedlocated at the centre of its city
Clarington
BTDR Clarington, OH
Approximate area: this is the town named in the filing, not the site.
Imagery: NASA Blue Marble, a 2004 global composite, and in the United States USGS aerial imagery, a mosaic of different dates. No single imagery date applies, and the site may have changed since. A flat view of the ground: no terrain.
- Energized
- 0 MW
- Nameplate
- 570 MW
- Stage
- announced
- Power source
- grid
- Ownership
- owned
- Grid operator
- PJM
- Announced
- Jul 3, 2024source dated Jul 3, 2024
- Place named in the filing
- Clarington, OHlocated at the centre of its city
Source: 6-K EX-99.1 Aug 10, 2026 (Q2 2026 unaudited results); read Sep 6, 2026.
Company photos: any pictures are in the filing above or on the company page. They belong to the company and are not copied here.
MARA